HOME  
 

CLIPEX
 
EXPERIMENT'S NAME
CLay Instrumentation Programme for the EXtension of an underground research laboratory
LAST MODIFIED
2004-02-05
EXPERIMENT'S ACRONYM
CLIPEX
TYPE OF TEST
Clay characterization
Instrumentation test
Construction technique

PERSON RESPONSIBLE
Name : Jan Verstricht
Email : jan.verstricht@sckcen.be

COLLABORATIONS
ANDRA, ENRESA, G.3S, GEOCONTROL, UPM

FINANCING ORGANISM(S)
EC, NIRAS/ONDRAF, ANDRA, ENRESA

GLOBAL BUDGET (k€)
~ 1200 (1997 – 2003)

Phenomena
Components
Safety (sub) functions concerned (if relevant)

i

Hydro-mechanical
Host rock
SF
D
L
SSF
C1
R1
ii
Construction methods
Host rock
SF
D
L
SSF
C1
R1
 
Background
The construction of the first shaft and the two galleries (URL and Test Drift) in the 1980’s has shown the feasibility of underground excavation and construction. Due to the pioneering nature of these works, this construction was performed in a fully manual way. An actual repository would require mechanised excavation techniques, allowing excavation at the higher excavation rate, at a lower cost when large lengths are considered. The extension of the underground research facility offered the opportunity to assess the performance of such an improved underground construction technique – the first deep (220 m) application of the wedge-block technique. A higher excavation rate would also result in a reduced perturbation of the host rock and hence, a reduced extent of the excavation damaged zone (EDZ). As the connecting gallery has been excavated from the second shaft, a unique opportunity was given to monitor the hydro-mechanical parameters ahead of the face of the connecting gallery. This measurement programme was complemented with model predictions to assess our capability to predict the hydromechanic response of the host rock to the gallery excavation and construction.
 
Objective of the experiment
The objective of the overall CLIPEX project is to assess the hydromechanical response of the Boom Clay host rock to the gallery excavation and construction, where a novel technique is applied. This is accomplished by an extensive measurement programme, complemented with model predictions. The resulting data should give us a better view on the (improved) performance of the new technique, and on the performance of the current models describing the hydro-mechanical response of the Boom Clay host rock to gallery excavation.CLIPEX has concentrated on operational aspects (gallery construction and its short-term influence on the host rock), rather than long-term safety aspects.
 
Description of the experiment

Design:


Figure 1 Location of CLIPEX instrumentation boreholes

Geotechnical sensors were installed in two major zones in the Boom Clay: eight instrumented boreholes installed from the front of the Test Drift, and two instrumented boreholes installed from the second shaft. In addition, three rings of the lining of the connecting gallery were constructed with instrumented segments.

Test Drift Front

From the shotcreted front, four subzones were instrumented in May 1998 with pressure and displacement transducers. Each subzone contained two 30 m-deep boreholes: one for pressure measurements (blue on the figure), and one borehole to monitor displacements (purple). The first zone “A” was located in the axis of the connecting gallery. An extensometer was installed in borehole A1. In the borehole, six anchors were installed at a depth between 20 and 30 m. Each anchor, from the geotextile packer type, was connected with a displacement transducer located in the measurement head at the front.


Figure 2 Installation and injection of extensometer packer anchors

The pore water pressures at six locations between 20 and 30 m were measured through filters integrated in the borehole casing of the pressure borehole A2, through the so-called multipiezometer. At three depths in this borehole, the total pressure was measured through miniature total pressure sensors which were also integrated in this borehole casing. At each depth, three sensors were installed.


Figure 3 Detail of piezometer casing, with filter and total pressure transducers

The second zone “B” was located slightly inclined above the connecting gallery. The vertical deformation towards the gallery was to be monitored by an inclinometer in borehole B1. This inclinometer consisted of a chain of 10 3 m-long segments, each equipped with an electrolevel sensor, and was installed permanently in a plastic (ABS) inclinometer casing. The pore water and total pressures were measured through borehole B2, which had a design similar to A2.


Figure 4 Inclinometer ABS casing (left) and electrolevel sensor (right)

The third zone “C” was located more inclined above the connecting gallery, and contained also an inclinometer in borehole C1, and a multipiezometer with integrated total pressure sensors in borehole C2. After completion of the excavation and lining of the gallery, the filters have been reconnected to the pressure transmitters and they continue to provide us with pore pressure measurements around the connecting gallery.The fourth zone “D” was located in the horizontal plane, towards the west (right when looking at the front of the Test Drift) with respect to the connecting gallery axis. The expected movement towards the gallery was measured through an deflectometer in borehole D1. This deflectometer consisted of a chain of 11 three m-long segments, connected to each other by angle transducers, and installed in a permanent way in the borehole casing. Borehole D2 was equipped with a multipiezometer with integrated total pressure sensors. As for C2, the filters of D2 have been reconnected to the pressure transmitters after completion of the excavation and lining of the gallery.


Figure 5 Global view at Test Drift Front, with the different instrumentation boreholes

Instrumentation installed from the second shaft

From the bottom part of the second shaft, two horizontal boreholes have been drilled and instrumented a few metres above the connection gallery (zone “E”). Borehole E1 is 30 m long and contains an in-place inclinometer with 15 2 m-long segments, equipped with electro-level sensors. Due to an unsufficient strength of the casing, we had to redrill this borehole, and equip it with a double casing (outer steel casing in addition to the inclinometer casing).Borehole E2 is 21 m deep and contains seven filters to measure the pore water pressure. Both instruments are still working.Some other instruments were also installed near the bottom of the second shaft, such as cells measuring the total pressure on the lining of the second shaft. This instrumentation is discussed in the part on the second shaft, but they showed also interesting results related to the construction of the connecting gallery.


Figure 6 Instrumentation boreholes in the lower part of the second shaft: piezometer E2 (up) and borehole for inclinometer (down); at right: borehole survey to measure the exact location of the borehole

Instrumented lining segments

To monitor the pressure build-up on the lining of the connecting gallery, three rings (nos. 15, 30 and 50) were constructed with instrumented segments. All ten segments of these rings (except the key segments) were equipped with vibrating wire strain gauges cast in the concrete. In addition to the global strain, the configuration also allowed to measure intrados and extrados strains separately, so that bending of the segments could also be monitored.


Figure 7 Cage instrumented with strain gauges; (right) cage in segment mould during casting of segment

 
Protocol/explanation :
  • Characterisation of the clay host rock through pressuremeter, dilatometer, and hydrofrac methods in boreholes from Test Drift front in May 1998. Self-boring pressuremeter tests in January 1999. The results were to be used in the modelling exercises.
  • Modelling of the excavation at different levels of complexity. Simple, 1-D predictions to compare modelling tools, and to assist to the design of the instrumentation programme (location of sensors, magnitudes of change). Complex modelling, up to 3-D, to predict the actual host rock behaviour with respect to the actual geometry and excavation procedure.
 
Instrumentation :
cf. supra (“description of the instrument”)
 
Status/timing/planning :
  • Instrumented boreholes from the Test Drift front installed in May 1998.
  • Instrumented boreholes from the second shaft: E1 instrumented in June 2001, E2 installed in October 2000.
  • Construction of mounting chamber in August 2001.
  • Excavation of connecting gallery from end January to 8 March 2002.
 
Associated works :
  • Construction of the second shaft
  • Construction of the connecting gallery
  • Long-term monitoring around connecting gallery (reference piezometers)
  • PRACLAY tests (especially gallery excavation)
 
Results of the experiment :

A lot of measurement data were obtained, and were compared with the model predictions. The performance of the sensors depended on the type of instrument. The porewater pressure measurements were very succesful, and showed the different stages during the excavation (pressure increase, pressure drop, up to suction, and finally atmospheric pressure). The total pressure sensors showed values similar to the porewater pressure, and therefore we could not derive any meaningful value for the effective pressure. Probably the measurement technique (integration of total pressure sensors in borehole casing) is not optimal, although the actual sensors performed quite well. The displacement measurements from the Test Drift front gave rather qualitative indications, as they were not completely adapted to the host rock environment. Inclinometer and deflectometer casing, as well as extensometer anchors and connection rods, should be adapted to the specific clay conditions.


Figure 8 Pore pressure evolution recorded by borehole C2 when the tunneling machine passed along; filter WC8 is most close to the gallery, and therefore has shown the largest variations

The inclinometer E1, where we had improved the casing, gave very satisfying results, showing very clearly the clay subsidence due to the excavation of the mounting chamber and the connecting gallery. Also the piezometer E2 provided us with very valuable results.


Figure 9 Settlement above the connecting gallery as recorded by the inclinometer E1 when the excavation of the connecting gallery started

The strain gauges in the lining segments are all still giving reliable strain data. They showed the stress rapid build-up of stress on the lining (within a few weeks), and also gave indications on bending of these segments, which seems to be related to the ring geometry. In order to include the creep and shrinkage behaviour of the concrete, an independent strain – stress characterisation (over one year) has been running.


Figure 10 Evolution of the external pressure on ring 50 as derived from the strain readings; the inset shows the average strain for the intrados and extrados gauges, showing a clear bending

When we compare the measurements with the model predictions, it appears that the current models underestimate the effects of the excavation. We are currently checking if newer models can give a better agreement with the observations.

Figure 11 Comparing the observed data with the model predictions shows a large underestimation of the excavation impact on the pore water pressures in the Boom Clay

 
Conclusions :

The instrumentation programme has given a wealth of information on the behaviour of the Boom Clay around the excavation. The experience gained with the instrumentation will allow us to improve future instrumentation programmes (such as the PRACLAY tests).

The actual measurements have also indicated the validity of the current models, and have pointed out the main issues to improve more these models :

  • A classical elasto perfect plastic model can't represent the plastic behavior of Boom clay.
  • The fracturing phenomenon, which should modify consequently the permeability in the massif and, especially modify the hydro-mechanical boundary conditions, should be taken into account.
  • The viscosity behavior must play a role in the pore pressure prediction.
  • Non saturated hydromechanical behavior around the gallery due to the de-saturation should be considered also.

Implications of the results

  • Supplementary (new) experiment(s) expected.
    not relevant at this moment.
  • Implications on the concepts (for HLW storage) studied.
    not relevant at this moment.
  • Ondraf/Niras’s acceptance criteria’s (not yet relevant)
    not relevant at this moment.
 
Bibliography :
  • F. Bernier, X.L. Li, J. Verstricht, J.D. Barnichon, V.Labiouse, W. Bastiaens, J.M.Palut, J.K. Ben Slimane, M. Ghoreychi, J. Gaombalet, F. Huertas, J.M. Galera, K. Merrien, F.J. Elorza & C. Davies. 2003. CLay Instrumentation Programme for the EXtension of an underground research laboratory, Final Report EC contract FI4W-CT96-0028, Luxembourg: European Commission.
  • Verstricht, J., Bastiaens, W., Bernier, F. & Li, X. L. 2003. A deep gallery excavation in clay: monitoring our modelling skills. In F. Myrvoll (ed.), Field Measurements in Geomechanics, Proc. of the 6th Int. Symp., Oslo (Norway), 15-18 September: 687-692. Lisse (The Netherlands): Swets & Zeilinger.
  • Verstricht, J. & Barnichon, J.-D. 1999. Modelling and monitoring of deep tunnelling in clay. In C.F. Leung, S.A. Tan & K.K. Phoon (eds), Field Measurements in Geomechanics, Proc. Int. Symp., Singapore, 1-3 December: 417-422. Rotterdam: Balkema.
  • Verstricht, J., Demarche, M. & De Bruyn, D. 2001. Extension of the Underground Research Facility for real-scale demonstration. Waste Management ’01, Proc. of the Int. Conf., Tucson, AZ (USA), 25 . February – 01 March.N:\DOKUMENT\ImageDb Geo\Publications\Jan\WM01_URF.doc
  • Barnichon, J.-D. & Volckaert, G. 2003. Observations and predictions of hydro-mechanical coupling effects in the Boom Clay, Mol Underground Research Laboratory, Belgium. Hydrogeology Journal, Vol 11-1, 193-202.N:\DOKUMENT\ImageDb Geo\Publications\Jan\Andra2000_HMcoupling.docF.
  • Bernier & L. Van Cauteren. 1998. Instrumentation programme near the face of an advancing tunnel in Boom Clay - Proceedings of the second international symposium on hard soils and soft rocks - Naples - 1998, A.A. Balkema, Rotterdam, 953-960.
  • Bernier, J. Verstricht & V. Labiouse. 1998, CLIPEX: CLay Instrumentation Programme for the Extension of an underground research laboratory., Proceedings of a cluster seminar: In-situ testing in underground research laboratories for radioactive waste disposal, Alden Biesen, European Commission, Nuclear Science and Technology, EUR 18323 EN, pp 25-37.
  • F. Bernier, J.D. Barnichon, J. Verstricht, D. De Bruyn. 1999. Extension of an underground research laboratory in clay: modelling and measurements of clay response. Euradwaste '99, Luxembourg, Proc. in press.