HOME  
 

RESEAL
 
EXPERIMENT'S NAME
A large scale in situ demonstration test for repository sealing in an argillaceous host rock
LAST MODIFIED
15/12/2003
EXPERIMENT'S ACRONYM
RESEAL
TYPE OF TEST
feasibility

PERSON RESPONSIBLE
Name : Maarten Van Geet
Email : mvgeet@sckcen.be

COLLABORATIONS
UPC, CIEMAT, CEA, ANDRA

FINANCING ORGANISM(S)
EC, NIRAS/ONDRAF

GLOBAL BUDGET (k€)
4000

Phenomena
Components
Safety (sub) functions concerned (if relevant)

i

Migration of radionuclides
EBS
SF
C
D
L
SSF
C1
C2
R1
ii
Migration of radionuclides
Host rock
SF
C
D
L
SSF
C1
C2
R1
iii
Hydro-mechanical
EBS
SF
D
L
SSF
C1
R1
iv
Hydro-mechanical
Host rock
SF
D
L
SSF
C1
R1
v
Gas generation and transport
EBS
SF
C
D
L
SSF
C1
C2
R1
vi
Demonstration
EBS
SF
D
L
SSF
C1
R1
 
Description of the experiment
 
Design:
 
Borehole sealing

 



 
 
Shaft sealing


 
 

Protocol/explanation :

Borehole sealing
The experimental set-up consists in a 250 mm diameter and 2.6 m long piezometer installed in the Test Drift of the HADES URL between 15m and 12.4m behind the lining. Only the first two meters of the piezometer are used for the sealing experiment. The set-up includes two testing compartments of 55 cm long with a central tube of about 56 mm diameter equipped with filters and total pressure sensors. The compartments are respectively filled in with pre-compacted blocks of Serrata clay and FoCa clay installed around the central tube. Total pressure measurements are done with miniature pressure sensors embedded in the set-up. Each filter is equipped with a separate chamber. Two pipes are connected on each chamber. One pipe is connected to a pressure sensor installed in the gallery of the URF and the other pipe is foreseen for water injection. The lateral faces of the compartments consist of circular filters in which total pressure sensors are included.

Shaft sealing
Starting from the URL HADES, an experimental shaft and experimental drift were excavated manually in 1984 to demonstrate the possibility of excavating a non-frozen plastic clay. This experimental shaft was chosen for the location of the large scale in-situ shaft sealing test. In april 1998, the installation of radial piezometers from the experimental shaft into the EDZ of the host rock took place. These radial piezometers are situated at the middle of the bentonite seal. These are 1m in length and contain several filters allowing to follow-up pore water pressure in the host rock at several distances from the lining-host rock interface. Very close to these radial piezometers, radial cores were taken for the emplacement of magnetic transducers between two clay cores for follow-up of the displacement. A vertical piezometer, parallel to the experimental shaft at about 1m from the shaft lining, was placed in june 1998. This is also a multifilter piezometer allowing pore water pressure follow-up beneath the bentonite seal, next to the seal and above the seal. In August 1999, the mining work for the installation of the seal has started. The shaft lining has been removed.over a height of 3.45 m (12.90 to 16.35 m below the HADES URL). After removal of the lining and the installation of the first section of the central tube, the shaft has been filled up with the FoCa bentonite mixture. The first 60 cm of the seal have been compacted. The compaction was stopped just below the first instrumented level. From this level the sealing material was installed without furhter compaction in order to avoid damage to the instruments due to the vibro compaction. On September 15th, 1999, a layer of 15 cm sand was placed on the mixture, followed by the hermetic closure of the seal with a resin layer. On top of the resin layer a reinforced-anchored concrete plug of about 1 m height has been installed.

 
Instrumentation :
  • Pore water pressure sensors
  • Total pressure sensors
  • Vertical displacement sensor of the top of the seaH
  • orizontal displacement sensors (magnetic transducers) for host rock displacement and displacement in the seal
 

Status/timing/planning :

Borehole sealing

  • December 1997: borehole drilling, piezometer installation and start of acquisition
  • March 1998: pressure increases measured
  • April 1998: start of water injection in the seals
  • September 1998: hydration stopped
  • February 1999: permeability tests
  • June 2002: 125I tracer injection
Shaft sealing
  • April 1998: installation of radial piezometers and displacement transducers
  • July 1998: installation of vertical piezometer
  • February 1998: backfilling of the bottom of the shaft with concrete
  • August 1999: removal of the lining
  • September 1999: installation of the seal and closing of the seal
  • May 2000: beginning of artificial hydration
Associated works :
  • Names of experiments :Bacchus
 
(Preliminary) Results of the experiment :
 

Borehole sealing
After hydration of the pre-compacted blocks of FoCa and Serrata clay, the permeability in the borehole seals was measured. A hydraulic conductivity of 4.3 10-13 ms-1 and 5.5 10-13 ms-1 was obtained for FoCa clay and Serrata clay, respectively. These values are 10 times lower than the hydraulic conductivity of undisturbed Boom Clay and are in good agreement with the laboratory measurements at the corresponding dry density. To test the gas sealing ability, a gas injection was carried out. Gas was injected in the host clay formation from a filter close to the FoCa seal compartment at the end of the borehole. The gas breakthrough occurred at a pressure level of about 3.1 MPa, i.e. a pressure equal to the radial total stress measured in the FoCa seal. The breakthrough has been detected on a filter in contact with Boom Clay, closer to the gallery. The pressure sensors connected to the filters in the FoCa seal show a very weak reaction to the breakthrough.

Shaft sealing

The relative humidity sensors inside the seal shows that the seal is near saturation after 4 years of artificial injection.

figure 1: Pore water pressure evolution in the filters of a radial piezometer. Before the removal of the lining a constant pore water pressure is observed. A sudden decrease in pore water pressure is noticed due to the removal of the lining. A slow re-increase of pore water pressure is later on noticed. This increase goes progressively from the furthest filter to the filter closest to the seal - host rock interface


Figure 2: Detail of figure 1 showing the sudden decrease in pore water pressure related to the removal of the lining, followed by a small increase in pore water pressure.

The installed piezometers provide quantitative data on the EDZ evolution around the seal (Fig. 1). The radial piezometers show, after installation and before removal of the lining, a quite constant pore water pressure, illustrating an equilibrium state. As a result of the removal of the lining a sudden decrease in the pore water pressure is noticed. The pore water pressure drops to a value lower than the detection limit of the measurement set-up. A more detailed view (Fig. 2) of the pore water pressure evolution shows a pressure increase following this sudden decrease. The time of occurrence for this sudden increase is related with the distance to the experimental shaft wall. The pressure evolution after this step and the curve of the air atmospheric pressure are qualitatively the same. This comparison indicates that at this time the sensors connected to the filters of the piezometer measure the atmospheric pressure. This means that there is a direct connection between the filter and the atmosphere. In other words, fractures have been developed through the host rock due to the decompression of the host rock around the shaft where the lining has been removed. The instrumentation was limited to 1 m around the shaft, showing that fractures occur at least up to 1 m distance from the shaft/clay interface.

 
Preliminary conclusions :
 

Borehole sealing
The permeability of the seals is a factor 10 lower than the permeability of the host rock formation and the behaviour of the seals under gas injection conditions confirm the feasibility of producing borehole seals. The experimental results have demonstrated that it is possible to seal with a bentonite material the excavation disturbed zone around a borehole.

Shaft sealing
The hydration of the sealing material takes much longer than originally foreseen. After 4 years of artificial hydration, several observations indicate a near saturation of the seal. The removal of the concrete lining has a strong effect on the EDZ. Fractures were formed around the shaft, causing many clay blocks to fall from the host rock wall. It is impossible to distinguish between re-activation of existing fractures (caused during excavation) and newly developed fractures caused by removal of the lining. The fractures in connection with atmospheric pressure occur up to at least 1 m depth in the host rock, but are limited to a cylindrical zone where the lining has been removed. The self-healing of the fractures is a slow process. However, it should be taken into account that the speed of self-healing can not be deduced from this RESEAL experiment, as here it is largely influenced by the hydration of the bentonite seal. The available data clearly show that the self-healing is a progressive process starting in the host rock and evolving towards the interface host rock - lining.

 
Bibliography :
  • Volckaert, G., Dereeper, B., Put, M., Ortiz, L., Gens, A., Vaunat, J., Villar, M.V., Martin, P.L., Imbert, C., Lassabatère, R., Mouche, E. and Cany, F., 2000. A large scale in situ demonstration test for repository sealing in an argillaceous host rock. RESEAL project - Phase I. European Commission, Luxembourg, EUR 19612, 273 pp.
  • Van Geet, M., Bastiaens, W., Volckaert, G., Vallejan, B. and Gens, A., 2003. Reconaissance study of EDZ around a large scale shaft sealing demonstration test (RESEAL). Impact of the Excavation disturbed or damaged zone (EDZ) on the performance of radioactive waste geological repositories: proceedings of a European Commission CLUSTER conference held in Luxembourg on 3-5 November 2003, EUR in press.